BIM Execution Plan (BEP) Framework
This BEP framework was developed for a 450,000 sq ft regional hospital project in Texas. It has been anonymized and generalized for use as a reference. The framework covers the minimum requirements that should appear in every project-specific BEP. Actual projects may require additional sections depending on owner requirements, delivery method, and local code constraints.
1. Project Information
| Project Name: | Regional Medical Center Expansion |
| Project Size: | 450,000 sq ft (6 floors + penthouse) |
| Delivery Method: | CM at Risk (GMP) |
| Coordination Duration: | 14 weeks (design-assist through MEP rough-in) |
| BIM Coordinator: | MEP Estimation USA (designated senior coordinator) |
2. Software & File Standards
| Authoring: | Autodesk Revit 2024 |
| Federation & Clash Detection: | Navisworks Manage 2024 |
| Collaboration: | Autodesk BIM 360 / ACC |
| File Format: | Revit .rvt (native); Navisworks .nwf (federated) |
| Coordinate System: | NAD83 State Plane Texas South Central (FIPS 4204), US Survey Foot |
3. LOD Responsibility Matrix
Each discipline's model must meet a minimum LOD at each project phase. LOD per AIA G202-2013.
| Discipline | SD (Responsible) | DD (Responsible) | CD/Coordination (Responsible) | Fabrication/Install (Responsible) |
|---|---|---|---|---|
| Architectural | LOD 200 (AOR) | LOD 300 (AOR) | LOD 350 (AOR) | LOD 350 (AOR) |
| Structural | LOD 200 (SOR) | LOD 300 (SOR) | LOD 350 (SOR) | LOD 350 (SOR) |
| Mechanical (Duct) | LOD 200 (MEP) | LOD 300 (MEP) | LOD 350 (MEP) | LOD 400 (Fabricator) |
| Mechanical (Piping) | LOD 200 (MEP) | LOD 300 (MEP) | LOD 350 (MEP) | LOD 400 (Fabricator) |
| Electrical | LOD 200 (MEP) | LOD 300 (MEP) | LOD 350 (MEP) | LOD 400 (Fabricator) |
| Plumbing | LOD 200 (MEP) | LOD 300 (MEP) | LOD 350 (MEP) | LOD 400 (Fabricator) |
| Fire Protection | LOD 200 (MEP) | LOD 300 (MEP) | LOD 350 (MEP) | LOD 400 (Fabricator) |
| Medical Gas | LOD 200 (MEP) | LOD 300 (MEP) | LOD 350 (MEP) | LOD 400 (Fabricator) |
4. Clash Test Configuration
| Selection Set A | Selection Set B | Tolerance | Type | Priority |
|---|---|---|---|---|
| Ductwork | Structure | 3" | Hard | P1 - Critical |
| Piping (all) | Structure | 3" | Hard | P1 - Critical |
| Ductwork | Piping | 3" | Hard | P2 - High |
| Electrical (cable tray) | Structure | 3" | Hard | P2 - High |
| Ductwork | Electrical (conduit) | 6" | Soft (clearance) | P3 - Medium |
| Piping | Electrical (conduit) | 6" | Soft (clearance) | P3 - Medium |
| Medical Gas | All trades | 3" | Hard | P1 - Critical |
| Equipment | All trades | 12" | Soft (access) | P2 - High |
Note: Our experience across 500+ coordinated projects shows that over-tight clearance tolerances (1-2") increase coordination effort by 30-40% without proportional construction benefit. The 3" hard clash / 6" soft clearance standard balances rigor with practical constructability.
5. Coordination Meeting Schedule
| Phase | Frequency | Duration | Key Milestone |
|---|---|---|---|
| Model QC (Week 1) | Once | 2 hours | Model Quality Report accepted by all trades |
| Initial Coordination (Weeks 2-6) | Weekly | 90 min | Clash count below 500 |
| Detailed Coordination (Weeks 7-11) | Weekly | 90 min | Clash count below 50 |
| Prefab Gate Review (Week 12) | Once | 2 hours | Zero open clashes per zone |
| Close-Out Review (Week 14) | Once | 1 hour | Final coordinated model + as-built log |
| Post-Award (ongoing) | Monthly | 60 min | Field verification updates |
6. Prefabrication Gate Criteria
No MEP prefabrication release is authorized until ALL of the following criteria are met for the release zone:
- Clash-free: Zero open hard clashes in the release zone. All soft (clearance) clashes documented and trade-accepted.
- LOD verified: All system elements in the release zone modeled at minimum LOD 400 (fabrication-level detail including hangers, supports, connections).
- Field-verified: Model-to-field accuracy confirmed within 1" for at least 20% of MEP tie-in points in the release zone (laser scan or physical measurement).
- Fabricator-ready: Federated model exported to fabricator's native format (SDS/2, CAMduct, TrimPipe) and confirmed compatible by the fabricator.
- BEP-compliant: Model file naming, version, and status meet BEP file standard requirements.
- Approved: Gate release form signed by GC BIM lead, MEP coordinator, and fabricator representative.
7. Responsibilities Matrix
| Task | GC | Design Team | MEP Coord | Subs |
|---|---|---|---|---|
| Model Federation (Navisworks) | P | - | S | - |
| Clash Detection Setup | P | - | S | - |
| Initial Clash Review & Triage | - | - | P | C |
| Model Updates (trade-specific) | - | C | - | P |
| Coordination Meeting Facilitation | P | C | S | C |
| Clash Resolution Documentation | - | - | P | C |
| As-Built Model Updates | - | - | S | P |
P = Primary / S = Support / C = Collaborate
Source: This BEP framework was developed from direct coordination experience on a 450,000 sq ft healthcare project. Anonymized and generalized for reference. Actual project BEPs should be customized to your specific project delivery method, owner requirements, and trade subcontractor capabilities.
Prepared by the MEP Estimation USA Preconstruction & VDC Group. Incorporating LOD 350-400 trade responsibility frameworks, federated model clash protocols, and prefabrication milestones.