HEALTHCARE — TEXAS
450,000 sq ft Regional Hospital
Full MEP coordination at LOD 350 across 9 trade models (architectural, structural, mechanical, electrical, plumbing, fire protection, medical gas, data/comm, food service).
2,847 clashes resolved over 14 coordination days — 203 clashes per day average.
Resolution breakdown: 58% duct vs. structure (operating room ceiling coordination), 22% pipe vs. structure, 12% duct vs. pipe, 8% electrical vs. all.
The most complex zone: the OR suite ceiling sandwich where HVAC, medical gas, electrical, and data competed for 4 ft of interstitial space.
Zero coordination-related change orders during MEP rough-in — contributing to a 2.5% total project change order rate vs. the 8–12% industry average.
Coordination investment: $0.58/sq ft. Change order savings estimated at $1.2M.
HIGH-RISE — NEW YORK
32-Story Class A Office Tower
LOD 400 coordination for prefabrication. 1,523 clashes resolved over 21 coordination days.
Clash density: 2.1 per 10,000 sq ft (below the 3.5 industry average for high-rise commercial).
Key challenge: MEP riser coordination within existing shaft dimensions that varied 4–8" from the drawings —
requiring laser scan integration before coordination could begin.
Prefabrication was released for 80% of ductwork and 65% of piping based on coordinated models.
Field verification confirmed model accuracy within 0.75" for 92% of prefabricated assemblies.
Coordination investment: $0.72/sq ft. Schedule compression: MEP rough-in completed 5 weeks ahead of baseline due to prefabrication.
INDUSTRIAL — GEORGIA
280,000 sq ft Manufacturing Plant
Process MEP coordination including industrial piping (ASME B31.3), compressed air, process cooling, and heavy electrical.
3,120 clashes resolved — the highest density we've coordinated due to the ceiling sandwich in the manufacturing bay:
process piping, compressed air, exhaust duct, electrical bus duct, fire protection, and lighting in a 6 ft plenum.
Resolution approach: gravity-dependent process piping got routing priority, compressed air and electrical bus duct rerouted.
Coordination included 4D sequencing for phased installation (manufacturing equipment installation ongoing during MEP rough-in).
Coordination investment: $0.65/sq ft. Change orders: 3.8% vs. estimated 11% without coordination.
DATA CENTER — ILLINOIS
180,000 sq ft Critical Facility
Critical MEP coordination for a Tier III data center. 1,890 clashes resolved —
primarily in the ceiling plenum above server halls where chilled water piping, electrical busway, cable tray, and fire suppression competed for space.
Highest clash density was between chilled water piping (4 x 8" mains) and electrical busway (2 x 4,000A runs) in the main distribution corridor.
Solution: busway routed above chilled water with 12" clearance for maintenance access.
Coordination at LOD 400 enabled 100% prefabrication of chilled water piping (42 spool pieces) —
zero field welds required. Commissioning completed 2 weeks early.
Coordination investment: $0.95/sq ft (data center premium). Estimated avoidance: $2.8M in potential conflict-related downtime.